Al-Yaseen United General Contracting Ltd

شركة الياسين المتحدة للمقاولات العامة المحدودة

This page sets out what the documents in this archive record about this company: the legal status on the date shown, the cases, the official registers and the sources.

Legal status as of 20 October 2026

Disciplined by an official body

Fined, suspended or otherwise punished by an administrative body.

What the documents say

The audit board said the company did not meet its contract; the director general approved withdrawing the work and referring the company to the blacklisting committee, and the Union Bank of Iraq confiscated its guarantee, though the money had not reached the distribution company's account when the report was written. An administrative measure, not an accusation of a crime.

Kind
Company
Roles
  • Supplier of poles and cables to the Middle distribution company (contract 276 of 27 December 2023, IQD 63.975 billion)

Cases

These are the cases in this archive that name this entry, with the status in each case on the date shown.
Cases
CaseRoleStatus in this caseDetailAs of
Board of Supreme Audit 2025 annual report: Ministry of Electricity findings referred for investigation (Iranian payments account, Akkaz fuel system, substation contracts)Supplier of poles and cables to the Middle distribution company (contract 276 of 27 December 2023, IQD 63.975 billion)Disciplined by an official bodyThe audit board said the company did not meet its contract; the director general approved withdrawing the work and referring the company to the blacklisting committee, and the Union Bank of Iraq confiscated its guarantee, though the money had not reached the distribution company's account when the report was written. An administrative measure, not an accusation of a crime.19 October 2026

Dated events

Each recorded step in the legal record of this entry is listed here in order of date.
  1. 11 June 2025
    Disciplined by an official bodyWork withdrawn and company referred for blacklisting, according to Federal Board of Supreme Audit report No. 29778

Documents

These are the documents behind this entry. Each quote is given in the language of the document.
  1. Federal Board of Supreme Audit22 July 2026Audit reportTier A

    التقرير السنوي لديوان الرقابة المالية الاتحادي لسنة 2025 (وزارة الكهرباء، الصفحات من 232 إلى 253)

    قيام الوزارة ونتيجة للعقوبات الامريكية بدفع مستحقات شركتي ( تافانير ، NIGC ) الإيرانية بموجب كتب تحويل الى حساب الشركتين المذكورة في المصرف العراقي للتجارة
    DocumentOriginal addressSHA-256 d73671625d4f