Board of Supreme Audit 2025 annual report: Ministry of Electricity findings referred for investigation (Iranian payments account, Akkaz fuel system, substation contracts)

The Federal Board of Supreme Audit's annual report for 2025, published on 22 July 2026, lists findings on the Ministry of Electricity, many of which it recommended be investigated. It found that, because of US sanctions, the ministry paid the Iranian companies Tavanir and NIGC by transfer letters into their account at the Trade Bank of Iraq instead of by letters of credit; the account held USD 818.17 million on 31 December 2024 and was left out of the ministry's cash statement. The ministry booked IQD 2.84 trillion of oil barter for Iranian gas before the Board had audited the cargoes, IQD 131 billion more than the audited invoices. A USD 64.4 million direct contract for a crude-oil treatment system at the Akkaz gas power plant went to Sada al-Nujoom, an Iraqi intermediary rather than a manufacturer, contrary to a 2009 cabinet instruction. Two contracts with Rabban al-Safina were flagged: a USD 54.05 million Baghdad substations contract signed although the investments department had asked to wait, and USD 17.56 million paid to the company's bank in the UAE outside the letter of credit. In Maysan, 49 percent of the power received in 2023 was lost.

Period
From December 2021 to July 2026
Sector
Electricity and energy infrastructureAudit of ministry accounts and contracts
Kind of case
Audit finding
Jurisdiction
Federal Iraq

How the money moved, according to the sources

This account is the one given by the sources listed on this page. It is not the finding of a court.

Payments made outside letters of credit and outside the ministry's own cash statement, accounting entries made before cargoes were audited, direct contracts with intermediaries instead of manufacturers, contracts signed against internal advice, and high network losses.

What happened

The Board recommended that the listed findings be investigated and that the ministry follow the rules for government contracts. No Integrity Commission or court action on these specific findings is on record as of 19 October 2026.

Open questions

  • Why the Iranian payments account was kept outside the ministry's cash statement, and who authorised payment by transfer letter.
  • Whether the Integrity Commission opened cases on the Akkaz and Rabban al-Safina contracts.
  • Who owns Sada al-Nujoom and Rabban al-Safina.

People and companies

The table lists everyone this case names, with their legal status on the date shown. A status in this case does not carry over to any other case, and an accusation is not a conviction. How to read the status.
People and companies
NameRole in the caseLegal statusDetailAs of
Al-Yaseen United General Contracting Ltd
شركة الياسين المتحدة للمقاولات العامة المحدودة
Supplier of poles and cables to the Middle distribution company (contract 276 of 27 December 2023, IQD 63.975 billion)Disciplined by an official bodyThe audit board said the company did not meet its contract; the director general approved withdrawing the work and referring the company to the blacklisting committee, and the Union Bank of Iraq confiscated its guarantee, though the money had not reached the distribution company's account when the report was written. An administrative measure, not an accusation of a crime.19 October 2026
Sada al-Nujoom for Trade, Contracting and Oil Services Ltd
شركة صدى النجوم للتجارة والمقاولات والخدمات النفطية المحدودة
Contractor: crude-oil treatment system for the Akkaz gas power plant (contract 34 of 21 November 2023, USD 64.4 million)Not charged as of the date of writingNot charged as of the date of writing. The audit board said the production company contracted directly with an intermediary that does not make the equipment, contrary to a 2009 cabinet letter, and recommended an investigation; the finding concerns the contracting body.19 October 2026
Rabban al-Safina General Contracting Ltd
شركة ربان السفينة للمقاولات العامة المحدودة
Contractor: substations for the Baghdad distribution company (USD 54.05 million), the Middle distribution company (USD 19 million) and Karbala (IQD 16.35 billion)Not charged as of the date of writingNot charged as of the date of writing. The audit board found the Baghdad contract was signed although the investments and contracts department had asked to wait, and that USD 17.56 million was paid to the company's account at a bank in the UAE outside the letter of credit; it recommended investigation of both. The findings concern the contracting companies.19 October 2026
Tavanir (Iran)
تافانير
Iranian state power company paid by the ministryNot charged as of the date of writingNot charged as of the date of writing. Named as a payee: the audit board found the ministry paid it and NIGC by transfer letters into an account at the Trade Bank of Iraq rather than by letters of credit.19 October 2026
National Iranian Gas Company (NIGC)
شركة NIGC
Iranian supplier of imported gasNot charged as of the date of writingNot charged as of the date of writing. Named as a payee: the audit board found the ministry booked IQD 2.84 trillion of oil barter for its gas before the cargoes were audited.19 October 2026

Sources

These are the documents on which this case rests. Each quote is given in the language of the document.
  1. Federal Board of Supreme Audit22 July 2026Audit reportTier A

    التقرير السنوي لديوان الرقابة المالية الاتحادي لسنة 2025 (وزارة الكهرباء، الصفحات من 232 إلى 253)

    قيام الوزارة ونتيجة للعقوبات الامريكية بدفع مستحقات شركتي ( تافانير ، NIGC ) الإيرانية بموجب كتب تحويل الى حساب الشركتين المذكورة في المصرف العراقي للتجارة
    DocumentOriginal addressSHA-256 d73671625d4f
  2. Rudaw29 July 2026Press reportTier D

    Iraq's supreme audit uncovers 530 financial impropriety cases worth some $30B

    The electricity ministry ranked second with 20 cases valued at 5.7 trillion IQD (about $4.4 billion)