People & Institutions
Lotka Construction Contracting Company and Saza Hi-Tech Esta South Company
Investment licence of the Baghdad Investment Commission, for the project: First Dreams City.
شركة لوتكة للمقاولات الانشائية وشركة سازة هاي تك ايستا جنوب
In short
This licence is held by Lotka Construction Contracting Company and Saza Hi-Tech Esta South Company, and was granted in 2010. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. No official finding, court case, sanctions designation or credible press accusation naming this licensee was found in the sources read. Status as of 19 October 2026.
The licence as listed
The list of licensed projects of the Baghdad Investment Commission.
- Licensing body
- Baghdad Investment Commission
- Licence number
- 24
- Date of grant
- 2010
- Sector
- Housing
- Project
- First Dreams Cityمدينة الاحلام الأولى
- Licensee
- شركة لوتكة للمقاولات الانشائية وشركة سازة هاي تك ايستا جنوب
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Baghdad
- Location
- 23/104 م16 هكتريا وشعار
- Holder of the land
- Abu Ghraib Municipalityبلدية ابي غريب
- Stated cost
- $229 million
- State of the project
- Under way (5% complete)
Who is behind the licensee
two companies licensed together; the commission calls the second a foreign investor
The owners and managers were not identified in the sources that were read.
What official and press reports say
- Official findings
- None found in the sources read.
- What became of the project
- The Baghdad Investment Commission list records licence no. 24 of 2010, First Dreams City, stated cost USD 229,000,000, land owner Abu Ghraib Municipality, location 23/104 م16 هكتريا وشعار, completion recorded as 5 per cent (under way). The Baghdad Investment Commission page on the chairman's tour of 24 June 2023 names the Al-Zaytoun residential complex of the same two companies. He ordered the problems to be solved, including water, electricity and sewage, and removal of encroachments, and told the companies that the commission would continue to ease matters for foreign investors. The page does not say whether Al-Zaytoun is the licence at issue or another project of the two companies.
- Other contracts with the state
- None found in the sources read.
Sources
- إستثمار بغداد : المهندس الحسن جميل يستمر بجولاته الميدانية للمشاريع الإستثماريةoriginal address, Baghdad Investment Commission (official website), 25 June 2023 Tier A
كما شملت الجولة ( مجمع الزيتون السكني) لشركة لوتكه سازة هاي وتك ايستا حيث أوعز الحسن بمعالجة وحل جميع مشاكل المشروع