This licence is held by Al-Imar and Al-Tatwir Real Estate, Tourism and Agricultural Investment Company, and was granted in 2016. The holder's documented legal status: "Not charged as of the date of writing". Published sources state one link between the holder and a politician, a party, an official or an armed group, set out below. A stated link is not a finding of wrongdoing.

The Baghdad Investment Commission page of 23 July 2023 lists the Al-Zahraa residential complex of the company among the projects its chairman visited on 22 July 2023. The page reports that the chairman would take legal steps, up to withdrawal of the licence, against investment companies proven to be slow, and does not say which companies are slow.

Legal status

Not charged as of the date of writing

Not charged as of the date of writing. No official finding, court case, sanctions designation or credible press accusation naming this licensee was found in the sources read. Status as of 19 October 2026.

The licence as listed

The list of licensed projects of the Baghdad Investment Commission.
Licensing body
Baghdad Investment Commission
Licence number
283
Date of grant
2016
Sector
Housing
Project
Fully serviced residential complex
مجمع سكني متكامل الخدمات
Licensee
شركة الاعمار والتطوير للاستثمارات العقارية والسياحية والزراعية
Licensee's official website
No official website found (searched 1 November 2026).
Province
Baghdad
Location
59 م2 زعفرانية
Holder of the land
Ministry of Finance
وزارة المالية
Stated cost
$93.6 million
State of the project
Not started (0% complete)

Who is behind the licensee

company (Iraqi company)

The owners and managers were not identified in the sources that were read.

Links stated in published sources

Each link is attributed to its source. A stated link is not a finding of wrongdoing.
  • The Baghdad Investment Commission page of 23 July 2023 lists the Al-Zahraa residential complex of the company among the projects its chairman visited on 22 July 2023. The page reports that the chairman would take legal steps, up to withdrawal of the licence, against investment companies proven to be slow, and does not say which companies are slow.

    مجمع الزهراء السكني) التابع لشركة الأعمار والتطوير للإستثمارات العقارية و( مجمع

    baghdadic.gov.iqoriginal address

What official and press reports say

Official findings
None naming this licensee as at fault. The commission's chairman announced on 22 July 2023 that legal steps would be taken against slow investment companies in general, without naming any. The Integrity Commission's prevention department said in a report on the Baghdad Investment Commission, carried by Alsumaria News on 8 June 2022, that the commission took no deterrent action against slow companies and limited itself to warnings for projects at 0 per cent completion. The report names no company.
What became of the project
The Baghdad Investment Commission list records licence no. 283 of 2016, Fully serviced residential complex, stated cost USD 93,550,950, land owner Ministry of Finance, location 59 م2 زعفرانية, completion recorded as 0 per cent (not started). The commission's page names the Al-Zahraa residential complex; the list gives 0 per cent. The page gives no licence number, so the match rests on the company name.
Other contracts with the state
None found in the sources read.

Sources

  1. إستثمار بغداد : زيارة ميدانية لعدد من المشاريع الإستثمارية وتوجيهات جديدة بالإنذار وسحب إجازات المتلكئينoriginal address, Baghdad Investment Commission (official website), 23 July 2023 Tier A
    مجمع الزهراء السكني) التابع لشركة الأعمار والتطوير للإستثمارات العقارية و( مجمع
  2. "توصيات واقتراحات".. النزاهـة تعلن نتائج زياراتهـا لهيئة استـثمار بغـدادoriginal address, Alsumaria News, 8 June 2022 Tier D
    بعدم اتخاذ هيئة استثمار بغداد إجراءاتٍ رادعةٍ بحقِّ الشركات المُتلكِّئة والاكتفاء بتوجيه إنذاراتٍ فقط للمشاريع التي كانت نسبة إنجازها (0%) وتفاوت في فرض بدلات الاستثمار لمشاريع