Iraq's Corruption
People & Institutions

Anwar Al-Sharqiya Plastics Production Company Ltd

Investment licence of the Baghdad Investment Commission, for the project: Factory for the production of plastics.

شركة انوار الشرقية لانتاج اللدائن المحدودة

All investment licences

In short

This licence is held by Anwar Al-Sharqiya Plastics Production Company Ltd, and was granted in 2017. The holder's documented legal status: "Not charged as of the date of writing". Published sources state one link between the holder and a politician, a party, an official or an armed group, set out below. A stated link is not a finding of wrongdoing.

The Baghdad Investment Commission publishes a project page of 20 October 2021 titled with the company's name. The page gives no further text.

Legal status

Not charged as of the date of writing

Not charged as of the date of writing. No official finding, court case, sanctions designation or credible press accusation naming this licensee was found in the sources read. Status as of 19 October 2026.

The licence as listed

The list of licensed projects of the Baghdad Investment Commission.
Licensing body
Baghdad Investment Commission
Licence number
380
Date of grant
2017
Sector
Industry
Project
Factory for the production of plastics
مصنع لانتاج اللدائن البلاستيكية
Licensee
شركة انوار الشرقية لانتاج اللدائن المحدودة
Licensee's official website
No official website found (searched 1 November 2026).
Province
Baghdad
Location
185 م19 شماعية وكرع / بعد التوحيد
Holder of the land
Amanat Baghdad (the Baghdad municipality)
امانة بغداد
Stated cost
$4.4 million
State of the project
Completed (100% complete)

Who is behind the licensee

company (Iraqi limited company)

The owners and managers were not identified in the sources that were read.

Links stated in published sources

Each link is attributed to its source. A stated link is not a finding of wrongdoing.
  • The Baghdad Investment Commission publishes a project page of 20 October 2021 titled with the company's name. The page gives no further text.

    شركة أنوار الشرقية للدائن المحدودة تخطي، > عربي (punctuation adjusted)

    baghdadic.gov.iqoriginal address

What official and press reports say

Official findings
None found in the sources read.
What became of the project
The Baghdad Investment Commission list records licence no. 380 of 2017, Factory for the production of plastics, stated cost USD 4,367,309, land owner Amanat Baghdad (the Baghdad municipality), location 185 م19 شماعية وكرع / بعد التوحيد, completion recorded as 100 per cent (completed). No source opened describes the factory's owners or its output.
Other contracts with the state
None found in the sources read.

Sources

  1. شركة أنوار الشرقية للدائن المحدودةoriginal address, Baghdad Investment Commission (official website), 20 October 2021 Tier A
    شركة أنوار الشرقية للدائن المحدودة تخطي، > عربي (punctuation adjusted)