In short

This licence is held by Al-Inbihar Real Estate and Agricultural Investment Company, and was granted in 2019. The holder's documented legal status: "Not charged as of the date of writing".

Legal status

Not charged as of the date of writing

Not charged as of the date of writing. No official finding, court case, sanctions designation or credible press accusation naming this licensee was found in the sources read. Status as of 1 November 2026.

The licence as listed

The list of licensed projects of the Baghdad Investment Commission.
Licensing body
Baghdad Investment Commission
Licence number
532
Date of grant
2019
Sector
Housing
Project
Fully serviced residential complex
مجمع سكني متكامل الخدمات
Licensee
شركة الانبهار للاستثمارات العقارية والزراعية
Licensee's official website
No official website found (searched 1 November 2026).
Province
Baghdad
Location
2/332 البو جمعة
Holder of the land
Amanat Baghdad (the Baghdad municipality)
امانة بغداد
Stated cost
$76.2 million
State of the project
Not started (0% complete)

Who is behind the licensee

company (Iraqi real estate and agricultural investment company)

The owners and managers were not identified in the sources that were read.

What official and press reports say

Official findings
None found in the sources read.
What became of the project
The Baghdad Investment Commission list records licence no. 532 of 2019, Fully serviced residential complex, stated cost USD 76,235,707, land owner Amanat Baghdad (the Baghdad municipality), location 2/332 البو جمعة, completion recorded as 0 per cent (not started). The commission names Al-Inbihar Real Estate and Agricultural Investment Company, in exactly the words of this licence, as the company carrying out the Murano residential complex at Arsat Al-Hindiya, on the Tigris. On 2 August 2021 it described the complex as a housing project licensed by the commission, of 150 units in five buildings of 16 floors each, and on 28 September 2022 it reported the opening of the sales centre for a complex of six buildings of 16 floors with shops on the ground floor and a car park. This is the company's only housing licence in the list, so the Murano complex may be this licence, but neither page gives a licence number and the list gives the location as plot 2/332 Al-Bu Juma'a, so this is not confirmed. No source opened gives the present state of the complex.
Other contracts with the state
The list holds licence no. 147 of 2012, a five-star restaurant on Abu Nuwas Street (USD 5,647,941, recorded as not started), in the name of Al-Inbihar Real Estate and Agricultural Investment and Industrial Project Rehabilitation Company LLC.

Sources

  1. أحد مشاريع الإسكان الإستثمارية الواعدة الممنوحة إجازة من قبل هيئة إستثمار بغداد والتي تحظى بدعم ورعاية رئيسها المهندس حيدر الأنصاريoriginal address, Baghdad Investment Commission (official website), 2 August 2021 Tier A
    توثيق مراحل العمل في مشروع ( مجمع مورانو السكني ) المنفذ من قبل ( شركة الإنبهار للإستثمارات العقارية والزراعية ) في العرصات / شارع المسبح
  2. تغطية لفعاليات إفتتاح مركز مبيعات مشروع ( مجمع مورانو السكني )original address, Baghdad Investment Commission (official website), 28 September 2022 Tier A
    حيث يتكون من (٦) بنايات سكنية بواقع (١٦) طابق لكل بناية أضافة الى طابق أرضي للوكالات التجارية و مرأب للسيارات