Investment licence of the Baghdad Investment Commission, for the project: Rehabilitation of a plant for producing concrete railway sleepers.
خضير كاظم برهان وعماد كاظم برهان
In short
This licence is held by Khudhair Kadhim Burhan and Imad Kadhim Burhan, and was granted in 2010. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
No charge, official finding, court case, sanctions designation or credible press accusation naming these licensees was found in the sources read. Status as of 2 November 2026.
The licence as listed
The list of licensed projects of the Baghdad Investment Commission.
- Licensing body
- Baghdad Investment Commission
- Licence number
- 37
- Date of grant
- 2010
- Sector
- Industry
- Project
- Rehabilitation of a plant for producing concrete railway sleepersتأهيل معمل لانتاج العوارض الكونكريتية للسكك الحديد
- Licensee
- خضير كاظم برهان وعماد كاظم برهان
- Province
- Baghdad
- Location
- معمل العوارض الكونكريتية للسكك الحديدية في ابو غريب
- Holder of the land
- Ministry of Transportوزارة النقل
- Stated cost
- $15 million
- State of the project
- Completed (100% complete)
Who is behind the licensee
two individuals licensed together
| Name | Role | Legal status | Source |
|---|---|---|---|
Khudhair Kadhim Burhan خضير كاظم برهان | Co-licensee (Baghdad Investment Commission licence for rehabilitating a concrete sleeper plant, USD 15,000,000) | Not charged as of the date of writing Not charged as of the date of writing. Nothing documented about this person was found in the sources read. Status as of 2 November 2026. | Not stated |
Imad Kadhim Burhan عماد كاظم برهان | Co-licensee (same licence) | Not charged as of the date of writing Not charged as of the date of writing. Nothing documented about this person was found in the sources read. Status as of 2 November 2026. | Not stated |
What official and press reports say
- Official findings
- None found in the sources read.
- What became of the project
- The Baghdad Investment Commission list records licence no. 37 of 2010, Rehabilitation of a plant for producing concrete railway sleepers, stated cost USD 15,000,000, land owner Ministry of Transport, location معمل العوارض الكونكريتية للسكك الحديدية في ابو غريب, completion recorded as 100 per cent (completed). No source found describes the project, its owners or its present state. The commission's page of 13 August 2022 on the industrial projects it has licensed lists the rehabilitation of a concrete railway sleeper plant at Abu Ghraib among them. The page does not name the holders and does not say how the plant stands today.
- Other contracts with the state
- None found in the sources read.
Sources
- إستثمار بغداد : ( ٤٤ ) مشروع إستثماري متميز ينعش القطاع الصناعي ويسير به نحو تحقيق التنميةoriginal address, Baghdad Investment Commission (official website), 13 August 2022 Tier A
تأهيل معمل إنتاج العوارض الكونكريتية للسكك الحديد في أبو غريب