Hiran General Contracting, General Trading and General Transport Company Ltd
Investment licence of the Baghdad Investment Commission, for the project: Residential complex.
شركة هيران للمقاولات العامة والتجارة العامة والنقل العام المحدودة
In short
This licence is held by Hiran General Contracting, General Trading and General Transport Company Ltd, and was granted in 2011. The holder's documented legal status: "Not charged as of the date of writing". Published sources state 2 links between the holder and a politician, a party, an official or an armed group, set out below. A stated link is not a finding of wrongdoing.
On 1 August 2023 the Baghdad Investment Commission chairman Al-Hasan Jameel Hasan received Parliament services committee member Mahdiya al-Lami and representatives of the Abu Al-Fadl residential complex in Al-Husseiniya, which Hiran carries out. The commission's page says the delay of the investing company and its cancellation of a number of contracts with buyers, who had protested in front of the governorate building, led the chairman to order an investigative committee into the complaint.
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. The Baghdad Investment Commission warned the company in May 2023 about delay, ordered an inquiry into buyers' complaints in August 2023 and withdrew the licence on 11 August 2024. On 29 July 2025, after recommendations of the National Investment Commission, it restored the licence and ordered the company to settle disputes with buyers and keep new delivery dates. The matter is a contract and delay dispute. No charge, court ruling, corruption finding or sanctions listing was found.
The licence as listed
- Licensing body
- Baghdad Investment Commission
- Licence number
- 100
- Date of grant
- 2011
- Sector
- Housing
- Project
- Residential complexمجمع سكني
- Licensee
- شركة هيران للمقاولات العامة والتجارة العامة والنقل العام المحدودة
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Baghdad
- Location
- 1/1501 م30 نهر عودة حسن
- Holder of the land
- Ministry of Financeوزارة المالية
- Stated cost
- $150 million
- State of the project
- Under way (3% complete)
Who is behind the licensee
The owners and managers were not identified in the sources that were read.
Links stated in published sources
On 1 August 2023 the Baghdad Investment Commission chairman Al-Hasan Jameel Hasan received Parliament services committee member Mahdiya al-Lami and representatives of the Abu Al-Fadl residential complex in Al-Husseiniya, which Hiran carries out. The commission's page says the delay of the investing company and its cancellation of a number of contracts with buyers, who had protested in front of the governorate building, led the chairman to order an investigative committee into the complaint.
لتأخر الشركة المستثمرة بإنجاز المشروع وإلغاءهم عدد من العقود مع المستفيدين منه
NIRIJ reported on 30 April 2025 that buyers say they were left in a cycle of delays. A buyer who signed in 2020 said the investor disappeared three months after the monthly instalments began and moved to Najaf to manage another project; the report gives this as the buyer's account. NIRIJ also quotes an unnamed official source who said Hiran only obtained the land contract and the licence and that another company, Tareeq Al-Harithiya, carried out the units and contracted with buyers on amended terms. The company did not comment in the report.
اختفى المستثمر تاركاً المشروع من دون إكمال
What official and press reports say
- Official findings
- Baghdad Investment Commission: final warning and 15 days to correct (May 2023); investigative committee into buyers' complaints (August 2023); withdrawal of the licence under the investment law (11 August 2024); reinstatement by administrative order no. 228 of 29 July 2025 after the National Investment Commission's grievance recommendations. A civil suit by the company against the commission was reported pending in April 2025. No court ruling, Integrity Commission or audit finding on Hiran was found. No charge, court ruling, sanction or official finding was found in the sources read.
- What became of the project
- The Baghdad Investment Commission list records licence no. 100 of 2011, Residential complex, stated cost USD 150,000,000, land owner Ministry of Finance, location 1/1501 م30 نهر عودة حسن, completion recorded as 3 per cent (under way). The project is the Abu Al-Fadl residential complex in Al-Husseiniya. NIRIJ, citing official documents, says the licence is no. 100 of 2011 for 200 dunums of Ministry of Finance land at USD 150 million, that a commission document of 20 September 2023 put actual completion at no more than 28 per cent, and that about 1,250 buyers are waiting. On 20 and 27 May 2023 the commission chairman gave Hiran and other delayed projects final warnings and 15 days to correct their work. The commission withdrew the licence on 11 August 2024 (Mawazin News; NIRIJ). Hiran sued the commission in September 2024. A commission grievance committee, on recommendations that the National Investment Commission sent in letters of 17 March, 15 April and 10 July 2025, accepted the company's grievance, and the commission's administrative order no. 228 of 29 July 2025 restored the licence and ordered the company to settle disputes with buyers and to deliver the first phase by the end of 2025.
- Other contracts with the state
- NIRIJ reports a buyer's claim that the investor moved to Najaf to run another project called Al-Hussein residential (1,000 units); no document for it was found. The site's housing register holds the Abu Al-Fadl licence as withdrawn.
Sources
- مشاريع الاستثمار المتلكئة في العراق: تفاقم أزمة السكن بدلا من حلها!original address, NIRIJ (Network of Iraqi Reporters for Investigative Journalism), 30 April 2025 Tier D
تكشف الوثائق الرسمية التي حصل عليها معد التحقيق، أن المشروع مُنح لشركة هيران للتجارة والمقاولات وفق إجازة استثمارية تحمل الرقم 100 لسنة 2011
- مشاريع الاستثمار المتلكئة في العراق: تفاقم أزمة السكن بدلا من حلها!original address, NIRIJ (Network of Iraqi Reporters for Investigative Journalism), 30 April 2025 Tier D
وأشارت وثيقة صادرة عن هيئة استثمار بغداد، في 20 أيلول/ سبتمبر 2023، إلى أن نسبة الإنجاز الفعلية في المشروع لم تتجاوز الـ 28 في المئة
- مشاريع الاستثمار المتلكئة في العراق: تفاقم أزمة السكن بدلا من حلها!original address, NIRIJ (Network of Iraqi Reporters for Investigative Journalism), 30 April 2025 Tier D
في المقابل، رفعت شركة هيران دعوى قضائية ضد الهيئة في أيلول/ سبتمبر2024 لدى محكمة البداءة في العاصمة بغداد، وهي ما زالت قيد النظر
- استثمار بغداد تعلن سحب اجازات ثلاثة مجمعات سكنية في العاصمةoriginal address, Mawazin News, 11 August 2024 Tier D
وكشف عن "سحب إجازة الاستثمار لمشروع مجمع أبو الفضل السكني الواقع في منطقة الحسينية وكذلك مجمع الزهور السكني وأيضاً مجمع المحبة"
- توضيح : ((حول مشروع ابو الفضل السكني الإستثماري ))original address, Baghdad Investment Commission (official website), 31 July 2025 Tier A
أصدرت هيئتنا أمرها الإداري بالعدد ( ٢٢٨ ) في ٢٠٢٥/٧/٢٩ الذي تقرر فيه إعادة العمل بالإجازة الإستثمارية وحل جميع الخلافات مع المستفيدين
- رئيس هيئة إستثمار بغداد يستقبل النائبة مهدية اللامي ولفيف من مستفيدي مجمع أبو الفضل السكنيoriginal address, Baghdad Investment Commission (official website), 2 August 2023 Tier A
لتأخر الشركة المستثمرة بإنجاز المشروع وإلغاءهم عدد من العقود مع المستفيدين منه
- إستثمار بغداد : الحسن جميل يوجه الشركات الإستثمارية المتلكئة برفع وتيرة العمل والإسراع بتنفيذ مشاريعoriginal address, Baghdad Investment Commission (official website), 28 May 2023 Tier A
أمهل الحسن إدارات هذه المشاريع ( ١٥) يوماً لتصحيح مسار عملهم