Attock Cement Pakistan Ltd and Al-Keetan Trading and Commercial Agencies Ltd (joint venture)

Investment licence of the Basra Investment Commission, for the project: Al-Kaitan Atok cement grinding and packing plant.

مشروع مشترك بين شركة أتوك للإسمنت الباكستانية وشركة الكيطان للتجارة والوكالات التجارية

All investment licences

In short

This licence is held by Attock Cement Pakistan Ltd and Al-Keetan Trading and Commercial Agencies Ltd (joint venture), and was granted in 2014. The holder's documented legal status: "Not charged as of the date of writing".

Legal status

Not charged as of the date of writing

The list does not name the holder; the name comes from a news report matched to the licence by project, place and cost. The list gives the holder's nationality as Iraqi and Pakistani, which fits the report. The name of the project joins the names of the two companies. No accusation, official finding, court case or sanctions listing about these companies in connection with the project was found in the sources read. Status as of 2 November 2026.

The licence as listed

The list of licensed projects of the Basra Investment Commission.
Licensing body
Basra Investment Commission
Licence number
91
Date of grant
22 April 2014
Documents of the licensing body
Sector
Industry
Project
Al-Kaitan Atok cement grinding and packing plant
معمل الكيطان اتوك لطحن وتعبئة الاسمنت
Licensee
مشروع مشترك بين شركة أتوك للإسمنت الباكستانية وشركة الكيطان للتجارة والوكالات التجارية (Iraqi and Pakistani)
Province
Basra
Area
60 dunums
Stated cost
$43.8 million
State of the project
Not reported

Who is behind the licensee

Joint venture. A trade report of 14 April 2014, eight days before the date of the licence, says Attock Cement Pakistan Ltd would own 60 per cent of the new company and Al-Keetan Trading and Commercial Agencies Ltd 40 per cent. The name of the project in the list joins the two names. The report does not give the name of the new company.

The owners and managers were not identified in the sources that were read.

What official and press reports say

Official findings
None about this project in the sources read.
What became of the project
A World Cement report of 14 April 2014 says Attock Cement Pakistan Ltd signed a joint venture agreement with Al-Keetan Trading and Commercial Agencies Ltd to build a grinding facility of 3,000 tonnes a day in Basra, at a cost its chief executive put at about USD 35 million, and that the plant could be working in a year. A World Cement report of 16 March 2015 says Pakistan's Economic Coordination Committee gave Attock Cement Pakistan Limited permission to set up a cement grinding unit in Iraq, and that the company proposed to send USD 24 million as equity for the plant in Basra. That report does not name the partner. No page read states whether the plant was built or opened.
Other contracts with the state
None found in the sources read.

Sources

  1. Attock Cement to set up a new grinding plant in Iraqoriginal address, World Cement (trade magazine), 14 April 2014 Tier B
    Attock Cement Pakistan Ltd has signed a joint venture agreement with Al-Keetan Trading and Commercial Agencies Ltd
  2. Attock Cement to build grinding plant in Iraqoriginal address, World Cement (trade magazine), 16 March 2015 Tier B
    ACPL proposed to remit US$24 million for the establishment of the plant in Basra