Ahl al-Wisal Company for Concrete Moulds, Steel Structures, Contracting, General Trade and Agricultural Services, Limited Liability

Investment licence of the National Investment Commission, for the project: Project for collection and maintenance of the electricity network for the districts of Al-Adhamiya and Hay Al-Qahira.

شركة أهل الوصال لصناعة القوالب الكونكريتية والهياكل الحديدية والمقاولات والتجارة العامة والخدمات الزراعية محدودة المسؤولية

All investment licences

Legal status

Not charged as of the date of writing

Not charged as of the date of writing. Owners and managers were not identified. No court ruling, Integrity Commission statement, audit finding, licence withdrawal, sanctions listing or credible press accusation naming this company was found in the sources read. A 2019 Integrity Commission call to review all electricity service and collection contractors named no company. The search of public sources is not complete. Status as of 5 October 2026.

The search of public sources on this licensee is not yet complete.

The licence as listed

The list of licensed projects of the National Investment Commission.
Licensing body
National Investment Commission
Licence number
228/2018
Date of grant
4 September 2018
Sector
Energy
Project
Project for collection and maintenance of the electricity network for the districts of Al-Adhamiya and Hay Al-Qahira
مشروع جباية وصيانة الشبكة الكهربائية لمحلات ( الاعظمية - حي القاهرة)
Licensee
شركة أهل الوصال لصناعة القوالب الكونكريتية والهياكل الحديدية والمقاولات والتجارة العامة والخدمات الزراعية محدودة المسؤولية (Iraqi)
Province
Baghdad
Location
بغداد
Stated cost
$5.5 million
The list gives the cost in dinars. It is converted here at 1,190 dinars to the dollar.
State of the project
Completed (100% complete)

Who is behind the licensee

company (Iraqi limited liability company, per the NIC list)

The owners and managers were not identified in the sources that were read.

What official and press reports say

Official findings
No finding about this company was found in the sources read. The NIC list records no obstacle or withdrawal for licence 228/2018. General context only: on 21 May 2019 the Integrity Commission called for a review of the performance of all service and collection companies contracted with the Ministry of Electricity, according to Alsumaria News. That statement named no company.
What became of the project
Licence 228/2018 (energy): مشروع جباية وصيانة الشبكة الكهربائية لمحلات الأعظمية وحي القاهرة, the project to collect fees for and maintain the electricity network in the Azamiyah and Hay al-Qahira neighbourhoods of Baghdad. Stated cost IQD 6,519,940,000, about USD 5.48 million at 1,190 dinars to the dollar (our arithmetic, tier B). The list writes the date as '9 April 2018'. Licence 225/2018 is dated 29/08/2018 and licence 230/2018 is dated 13/9/2018, so the date most likely reads 4 September 2018 with day and month transposed. The completion column reads '1', which the register reads as 100 per cent complete. On 12 January 2018 the head of the National Investment Commission, Sami al-Araji, said the profit of the collection companies is 12.5 per cent and that they must rehabilitate, develop and maintain the networks, with the rest going to the state (Non14). No public report on how this contract was carried out was found. Not verified in any other source.
Other contracts with the state
None found in the sources read. The NIC list shows no other licence under this name.

Sources

  1. النزاهة تطالـب بإعـادة النظـر في أداء شـركات الخـدمة والجبايـة التابعة للكهرباء, Alsumaria News, 21 May 2019 Tier D
    دعت هيأة النزاهة، الثلاثاء، إلى إعادة النظر في أداء شركات الخدمة والجباية المُتعاقدة مع وزارة الكهرباء
  2. سامي الأعرجي: شركات جباية اجور الكهرباء تأخذ 12,5 دولار من كل 100 دولار, Non14, republishing an Al-Ghad Press interview with Dr Sami al-Araji, head of the National Investment Commission, 12 January 2018 Tier C
    ارباحها 12,5% يعني تأخذ من كل 100 دولار 12,5 دولار وهي مطلوب منها تأهيل وتطوير وصيانة والبقية للدولة