Mass Energy Group Holding (Mass Group Holding, MGH; also Mass Global Energy)
Investment licence of the National Investment Commission, for the project: Construction of a gas-fired power station (1000 MW simple cycle + 2000 MW combined cycle), Bismayah, Baghdad.
مجموعة ماس القابضة للطاقة
In short
This licence is held by Mass Energy Group Holding (Mass Group Holding, MGH; also Mass Global Energy), and was granted in 2014. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this licensee or its owner was found in the sources read. The Cabinet decisions on the licence, the dues and the summer supply contract are recorded as facts. The owner is named by the International Finance Corporation and by Emirates Islamic. Absence of findings is not proof that none exist. Status as of 19 October 2026.
The licence as listed
- Licensing body
- National Investment Commission
- Licence number
- 40/2014
- Date of grant
- 26 March 2014
- Sector
- Energy
- Project
- Construction of a gas-fired power station (1000 MW simple cycle + 2000 MW combined cycle), Bismayah, Baghdadبناء محطة كهرباء غازية (1000 ميكاواط دورة بسيطة + 2000 ميكاواط دورة مركبة) بسماية/بغداد
- Licensee
- مجموعة ماس القابضة للطاقة (British)
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Baghdad
- Location
- بغداد، بسماية
- Stated cost
- $3 billion
- State of the project
- Not reported
Who is behind the licensee
| Name | Role | Legal status | Source |
|---|---|---|---|
Ahmed Ismail Saleh أحمد إسماعيل صالح | Chairman of Mass Group Holding, per Emirates Islamic (January 2026). Iraq Business News (16 September 2019) names Ahmad Ismail as chairman of Mass Energy Group Holding. An International Finance Corporation project page says the Mass group of companies is owned by Mr. Ahmed Ismail Saleh and his family. | Not charged as of the date of writing Not charged as of the date of writing. No charge, court ruling, sanction or official finding was found in the sources read. Status as of 19 October 2026. | Document (saved page)emiratesislamic.ae |
What official and press reports say
- Official findings
- No court ruling, Integrity Commission statement, audit bureau finding or parliamentary report naming the company was found. Official acts on record are the Cabinet approvals of the licence (February 2014), of the payment of dues (December 2018) and of the summer 2024 supply contract. None is a finding of wrongdoing.
- What became of the project
- The National Investment Commission list records licence 40/2014 dated 26 March 2014 for a gas power station of 1,000 MW simple cycle and 2,000 MW combined cycle at Bismayah, Baghdad, nationality British, at a stated cost of USD 3,000,000,000. Completion is listed by phase: the first phase of 1,000 MW at 100 per cent, the second phase of 500 MW at 100 per cent, the third phase of 1,000 MW at 100 per cent and the fourth phase of 500 MW at 53 per cent. No obstacle is recorded. Iraq Oil Report reported on 26 February 2014 that the Cabinet approved investment licences for two new power plants, 15-year build-own-operate contracts awarded by the National Investment Commission to two Iraqi companies: Shamara Group at Rumaila and Mass Global at Besmaya, 1,500 MW. In September 2019 Mass Energy Group Holding and GE signed an agreement for phase 3 of the Besmaya plant, which would take the total capacity to 4.5 GW, with power sold to the Ministry of Electricity under a 20-year power purchase agreement. Iraq Business News reported on 12 August 2025 that Prime Minister Mohammed Shia al-Sudani had inaugurated gas turbine unit 13 at the Bismayah plant, adding 300 MW, and gave the plant's total generation capacity as 5,000 MW, in coordination with Mass Group Holding.
- Other contracts with the state
- The International Finance Corporation page on MGES Power says Mass Energy Group Holding owns two other operating independent power plants in the Kurdistan Region, with a total installed capacity of 3,500 MW. The Council of Ministers decided on 24 June 2024 that the Ministry of Electricity would contract Mass Group Holding for three months to supply power to the northern region and the national grid for the summer peak (964). The Council of Ministers approved in December 2018 that the Ministry of Oil pay the dues of Mass Group Holding, USD 44.2 million, in black oil at world prices under the contract of 2017 (Mustaqila). In January 2026 Emirates Islamic announced a financing of USD 500 million for Mass Group Holding for a gas power plant in Romania.
Sources
- Iraq approves two IPP power plant dealsoriginal address, Iraq Oil Report, 26 February 2014 Tier D
The licenses for 15-year, build-own-operate contracts were awarded by Iraq’s National Investment Commission to two Iraqi companies. Shamara Group will build a 3,000 megawatt plant in Rumaila, in Basra province, and Mass Global will build a 1,500 megawatt plant in Besmaya, southeast of Baghdad
- Mass Global, GE to add up to 1.5 GW at Besmaya Power Plant | Iraq Business Newsoriginal address, Iraq Business News, 16 September 2019 Tier D
Mass Energy Group Holding (MGH) and GE Power signed a new agreement that will help establish Phase 3 of the Besmaya [Bismaya] Power Plant, taking the total capacity of the facility up to 4.5 gigawatts (GW).
- Mass Global, GE to add up to 1.5 GW at Besmaya Power Plant | Iraq Business Newsoriginal address, Iraq Business News, 16 September 2019 Tier D
MGH will supply electricity from the new extension of the plant to the Iraqi Ministry of Electricity under a 20-year power purchase agreement (PPA).
- Mass Global, GE to add up to 1.5 GW at Besmaya Power Plant | Iraq Business Newsoriginal address, Iraq Business News, 16 September 2019 Tier D
by Ahmad Ismail, Chairman of MGH
- Iraqi PM Inaugurates New Gas Turbine at Bismayah | Iraq Business Newsoriginal address, Iraq Business News, 12 August 2025 Tier D
Prime Minister Mohammed Shia Al-Sudani has inaugurated gas turbine unit No. 13 at the Bismayah Gas Power Plant, adding 300 MW
- Iraqi PM Inaugurates New Gas Turbine at Bismayah | Iraq Business Newsoriginal address, Iraq Business News, 12 August 2025 Tier D
bringing the plant's total generation capacity to 5,000 MW
- Iraqi PM Inaugurates New Gas Turbine at Bismayah | Iraq Business Newsoriginal address, Iraq Business News, 12 August 2025 Tier D
in coordination with Mass Group Holding (MGH)
- MGES Power (IFC project 37045)original address, Rights in Development, early warning system record of the International Finance Corporation project disclosure Tier D
Mass Energy Group Holding Limited is part of the Mass group of companies, owned by Mr. Ahmed Ismail Saleh and his family.
- MGES Power (IFC project 37045)original address, Rights in Development, early warning system record of the International Finance Corporation project disclosure Tier D
owner of two other operating independent power plants in the Kurdish Region of Iraq for a total installed capacity of 3500MW
- "الإمارات الإسلامي" ينجز صفقة تمويلية مهيكلة بقيمة 500 مليون دولار لصالح مجموعة ماس القابضةoriginal address, Emirates Islamic (press release), January 2026 Tier D
أحمد إسماعيل صالح، رئيس مجلس إدارة مجموعة ماس القابضة
- الحكومة تقرر التعاقد مع شركة “ماس” لتجهيز المنطقة الشمالية بالكهرباءoriginal address, 964 (statement of the Council of Ministers), 24 June 2024 Tier D
أُقر تعاقد وزارة الكهرباء مع (شركة ماس القابضة)، لتجهيز الطاقة الكهربائية للمنطقة الشمالية بشكل خاص، وللمنظومة الوطنية بشكل عام
- العراق يقرر تسديد تسديد مستحقات مجموعة ماسoriginal address, Mustaqila News Agency, 16 December 2018 Tier D
وافق مجلس الوزراء العراقي على قيام وزار النفط بتسديد مستحقات مجموعة ماس القابضة بما يعادلها من مادة النفط الأسود بالأسعار العالمية بموجب العقد 2017
- العراق يقرر تسديد تسديد مستحقات مجموعة ماسoriginal address, Mustaqila News Agency, 16 December 2018 Tier D
تبلغ مستحقات المجموعة 44.2 مليون دولار