Iraq's Corruption
People & Institutions

Tahsin Abdul-Zahra Salman

Investment licence of the National Investment Commission, for the project: Al-Shurooq commercial building.

تحسين عبد الزهرة سلمان

All investment licences

In short

This licence is held by Tahsin Abdul-Zahra Salman, and was granted in 2015. The holder's documented legal status: "Not charged as of the date of writing".

Legal status

Not charged as of the date of writing

Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this licensee was found in the sources read. The Basra Investment Commission names the investor in its own announcement of the licence. Owners and managers were not identified. Absence of findings is not proof that none exist. Status as of 19 October 2026.

The licence as listed

The list of licensed projects of the National Investment Commission.
Licensing body
National Investment Commission
Licence number
68/2015أ
Date of grant
24 November 2015
Sector
Commerce
Project
Al-Shurooq commercial building
مبنى الشروق التجاري
Licensee
تحسين عبد الزهرة سلمان (Iraqi)
Province
Basra
Location
محافظة البصرة
Stated cost
$3.8 million
The list gives the cost in dinars. It is converted here at 1,190 dinars to the dollar.
State of the project
Not started (0% complete)
The commission's remarks and obstacles
· تم استلام الأرض تم تعديل الأجازة لتقليل عدد الطوابق لحصول تعارضات والان في طور التنفيذ .

Who is behind the licensee

individual

The owners and managers were not identified in the sources that were read.

What official and press reports say

Official findings
None found in the sources read.
What became of the project
The National Investment Commission list records licence 68/2015أ dated 24 November 2015 for Al-Shurooq commercial building in Basra, sector commerce, nationality Iraqi, at a stated cost of IQD 4,543,800,000 (about USD 3,818,319 at 1,190 dinars to the dollar, our arithmetic, tier B). Completion is recorded as 0 per cent. The obstacle recorded is «تم استلام الأرض تم تعديل الأجازة لتقليل عدد الطوابق لحصول تعارضات والان في طور التنفيذ .», that is, the land was received and the licence was amended to reduce the number of floors because of conflicts, and the project was then in implementation. The Basra Investment Commission reported on 29 November 2015 that it handed the licence to the investor and that Ma' Al-Sama International Company would carry out the project in 20 months. The cost it gave, more than IQD 4,500,000,000, is consistent with the National Investment Commission figure of IQD 4,543,800,000. The National Investment Commission list says the licence was later amended to reduce the number of floors. No later public report on the building was found.
Other contracts with the state
None found. The National Investment Commission list shows no other licence for this licensee.

Sources

  1. إجازة استثمارية جديدة تمنح لمستثمر عراقي لإنشاء مبنى الشروق التجاريoriginal address, Basra Investment Commission (investbasrah.com), 29 November 2015 Tier A
    تم منح المستثمر تحسين عبد الزهرة سلمان الإجازة الاستثمارية المرقمة (68\2015) لإقامة مبنى الشروق التجاري و بكلفة تتجاوز الأربع مليارات و خمسمائة مليون دينار عراقي
  2. إجازة استثمارية جديدة تمنح لمستثمر عراقي لإنشاء مبنى الشروق التجاريoriginal address, Basra Investment Commission (investbasrah.com), 29 November 2015 Tier A
    ستقوم شركة ماء السماء الدولية بتنفيذ المشروع خلال فترة 20 شهر