Mawarid Investment and Supply Company
Investment licence of the National Investment Commission, for the project: Integrated residential complex.
شركة موارد للاستثمار والتوريد
In short
This licence is held by Mawarid Investment and Supply Company, and was granted in 2016. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this company was found in the sources read. The National Investment Commission list records that the investment contract was being signed and the plans amended. That is a stated project status and not an allegation. Owners and managers were not identified. Absence of findings is not proof that none exist. Status as of 19 October 2026.
The licence as listed
- Licensing body
- National Investment Commission
- Licence number
- 91/2016أ
- Date of grant
- 15 June 2016
- Sector
- Housing
- Project
- Integrated residential complexمجمع سكني متكامل
- Licensee
- شركة موارد للاستثمار والتوريد (Jordanian)
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Baghdad
- Location
- بغداد
- Stated cost
- $240 million
- State of the project
- Contract not signed (0% complete)
- The commission's remarks and obstacles
- · في طور توقيع العقد الاستثماري وتعديل مخططات المشروع لإضافة نشاط تجاري سياحي.
Who is behind the licensee
The owners and managers were not identified in the sources that were read.
What official and press reports say
- Official findings
- None found in the sources read.
- What became of the project
- The National Investment Commission list records licence 91/2016أ dated 15 June 2016 for an integrated residential complex in Baghdad, sector housing, nationality Jordanian, at a stated cost of USD 240,000,000. Completion is recorded as 0 per cent. The list marks the licence as: contract not signed. The obstacle recorded is «في طور توقيع العقد الاستثماري وتعديل مخططات المشروع لإضافة نشاط تجاري سياحي.», that is, the investment contract was being signed and the project plans were being amended to add a commercial and tourist activity. No report on the company or the project was found. The stated cost, USD 240,000,000, is among the largest for a housing licence in this part of the list.
- Other contracts with the state
- None found. The National Investment Commission list shows no other licence for this licensee.