This licence is held by Dar Al-Naba General Contracting Company, and was granted in 2017. The holder's documented legal status: "Not charged as of the date of writing".

Legal status

Not charged as of the date of writing

Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this company was found in the sources read. The National Investment Commission list records that the project was stopped because of a lawsuit between the Ministry of Youth and Sports and the Olympic Committee. The company is not a party to that lawsuit according to the list, and the entry is not an allegation against it. Owners and managers were not identified. Absence of findings is not proof that none exist. Status as of 19 October 2026.

The licence as listed

The list of licensed projects of the National Investment Commission.
Licensing body
National Investment Commission
Licence number
129/2017
Date of grant
6 April 2017
Sector
Sport and leisure
Project
Maysan sports club
نادي ميسان الرياضي
Licensee
شركة دار النبأ للمقاولات العامة (Iraqi)
Licensee's official website
No official website found (searched 1 November 2026).
Province
Maysan
Location
ميسان
Stated cost
$3.4 million
The list gives the cost in dinars. It is converted here at 1,190 dinars to the dollar.
State of the project
Not reported
The commission's remarks and obstacles
· متوقف بسبب وجود دعوى قضائية بين وزارة الشباب والرياضة واللجنة الاولمبية .

Who is behind the licensee

company (Iraqi general contracting company, as the National Investment Commission list names it)

The owners and managers were not identified in the sources that were read.

What official and press reports say

Official findings
None found in the sources read.
What became of the project
The National Investment Commission list records licence 129/2017 dated 6 April 2017 (the list gives a spreadsheet date, so day and month may be transposed) for Maysan sports club in Maysan, sector sport and leisure, nationality Iraqi, at a stated cost of IQD 4,100,000,000 (about USD 3,445,378 at 1,190 dinars to the dollar, our arithmetic, tier B). The obstacle recorded is «متوقف بسبب وجود دعوى قضائية بين وزارة الشباب والرياضة واللجنة الاولمبية .», that is, the project was stopped because of a lawsuit between the Ministry of Youth and Sports and the Olympic Committee. No report on the club or on the lawsuit was found. The National Investment Commission list names a dispute between two state bodies as the cause of the stoppage.
Other contracts with the state
None found. The National Investment Commission list shows no other licence for this licensee.