Anwar Al-Qurashi General Contracting Company Ltd
Investment licence of the National Investment Commission, for the project: Residential complex.
شركة أنوار القريشي للمقاولات العامة المحدودة
In short
This licence is held by Anwar Al-Qurashi General Contracting Company Ltd, and was granted in 2018. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this company was found in the sources read. The National Investment Commission list records that the procedures for signing the contract and handing over the site were not completed. That is a stated obstacle and not an allegation. Owners and managers were not identified. Absence of findings is not proof that none exist. Status as of 19 October 2026.
The licence as listed
- Licensing body
- National Investment Commission
- Licence number
- 200/2018
- Date of grant
- 8 May 2018
- Sector
- Housing
- Project
- Residential complexمجمع سكني
- Licensee
- شركة أنوار القريشي للمقاولات العامة المحدودة (Iraqi)
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Qadisiyah
- Location
- الديوانية
- Stated cost
- $24.5 million
- State of the project
- Contract not signed
- The commission's remarks and obstacles
- لم تستكمل إجراءات توقيع العقد وتسليم الموقع للمستثمر .
Who is behind the licensee
The owners and managers were not identified in the sources that were read.
What official and press reports say
- Official findings
- None found in the sources read.
- What became of the project
- The National Investment Commission list records licence 200/2018 dated 8 May 2018 (the list gives a spreadsheet date, so day and month may be transposed) for a residential complex in Qadisiyah, sector housing, nationality Iraqi, at a stated cost of USD 24,453,288. The list marks the licence as: contract not signed. The obstacle recorded is «لم تستكمل إجراءات توقيع العقد وتسليم الموقع للمستثمر .», that is, the procedures for signing the contract and handing the site to the investor were not completed. No report on the residential complex was found. The Basra commission's licence pages for a company called Anwar Al-Ibtisama are not this licensee.
- Other contracts with the state
- None found. The National Investment Commission list shows no other licence for this licensee.