Wangkang Holding Group Co. Ltd
Investment licence of the National Investment Commission, for the project: Construction of a plant for the production of ceramics.
Wangkang Holding Group Co.Ltd
In short
This licence is held by Wangkang Holding Group Co. Ltd, and was granted in 2018. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this company was found in the sources read. A 964 report of 3 June 2023 says the Babil Investment Commission withdrew the licence of a ceramics plant held by a Chinese company, which it does not name, after seven years of delay. The link to this licensee rests on the project type, the province and the nationality, and the dates do not fit well. The reason given is delay. No charge, court ruling, sanction or official finding was found in the sources read. Owners and managers were not identified. Absence of findings is not proof that none exist. Status as of 19 October 2026.
The licence as listed
- Licensing body
- National Investment Commission
- Licence number
- 213/2018
- Date of grant
- 9 July 2018
- Sector
- Industry
- Project
- Construction of a plant for the production of ceramicsإنشاء معمل لإنتاج السيراميك
- Licensee
- Wangkang Holding Group Co.Ltd (Chinese)
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Babil
- Location
- بابل
- Stated cost
- $71.5 million
- State of the project
- Contract not signed
- The commission's remarks and obstacles
- لم تستكمل إجراءات توقيع العقد وتسليم الموقع للمستثمر .
Who is behind the licensee
The owners and managers were not identified in the sources that were read.
What official and press reports say
- Official findings
- 964 reported on 3 June 2023 that the Babil Investment Commission withdrew the licence of a ceramics plant of a Chinese company, citing delay. The company is not named, and the link to this licensee rests on the project type and the nationality.
- What became of the project
- The National Investment Commission list records licence 213/2018 dated 9 July 2018 (the list gives a spreadsheet date, so day and month may be transposed) for Construction of a plant for the production of ceramics in Babil, sector industry, nationality Chinese, at a stated cost of USD 71,500,000. The list marks the licence as: contract not signed. The obstacle recorded is «لم تستكمل إجراءات توقيع العقد وتسليم الموقع للمستثمر .», that is, the procedures for signing the contract and handing the site to the investor were not completed. On 3 June 2023, 964 reported that the head of the Babil Investment Commission announced the halt of work on four projects and the withdrawal of their licences after seven years of delay, among them a ceramics plant of a Chinese company. The report does not name the company. A ceramics plant of a Chinese company in Babil fits this licence, but the licence is dated 2018, five years earlier, and no source ties the licensee to the withdrawal.
- Other contracts with the state
- None found. The National Investment Commission list shows no other licence for this licensee.
Sources
- بابل تعاقب شركة صينية ومستثمرين: استنفذوا كلّ الفرص ولا مكان لـ "المتلكئين"original address, 964 (Network 964), 3 June 2023 Tier D
الإجازات الاستثمارية التي تم سحبها هي؛ معمل إنتاج السيراميك لشركة صينية، فندق بابل بلازا لمستثمر محلي، معمل إنتاج القناني الزجاجية لمستثمر محلي ومركز تجاري لمستثمر محلي.
- بابل تعاقب شركة صينية ومستثمرين: استنفذوا كلّ الفرص ولا مكان لـ “المتلكئين”original address, 964 (Network 964), 3 June 2023 Tier D
المشاريع متلكئة منذ أكثر من 7 سنوات