Iraq's Corruption
People & Institutions

Raban Al-Safina for Energy Projects Ltd (RASEP), part of Raban Al-Safina Group

Investment licence of the National Investment Commission, for the project: Heavy fuel treatment for Wasit thermal power station.

شركة ربان السفينة لمشاريع الطاقة المحدودة

All investment licences

In short

This licence is held by Raban Al-Safina for Energy Projects Ltd (RASEP), part of Raban Al-Safina Group, and was granted in 2019. The holder's documented legal status: "Not charged as of the date of writing". Published sources state 2 links between the holder and a politician, a party, an official or an armed group, set out below. A stated link is not a finding of wrongdoing.

Mustaqila reported on 23 July 2026 that an unnamed source asked the Integrity Commission and the Federal Board of Supreme Audit to audit contracts obtained by companies of the Raban Al-Safina Group in the oil refining sector during the period of Adnan al-Jumaili as deputy oil minister for refining, to check supply prices, the need for the equipment and where it is used. The source also questioned the allocation of land for the group's factory at Owairij south of Baghdad and a USD 20 million loan from the Trade Bank of Iraq, without producing the decisions or the loan contract. Mustaqila said it could not verify this independently, that no technical documents or official reports support the claims, and that published judicial statements do not show the group or its founder accused in the al-Jumaili case. The statement is anonymous and the outlet is not one the project treats as credible. It names the group, not this licence, and is recorded as a statement, not as a finding.

Legal status

Not charged as of the date of writing

Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this licensee was found in the sources read. The National Investment Commission list records no obstacle. Two items touch the group and not this licence: an anonymous request, reported by Mustaqila in July 2026, that the Integrity Commission audit the group's refining contracts, which the report says is unverified and does not show the group accused; and 964's report of May 2026 on a conflict of interest, because the founder's son became Minister of Electricity while family companies hold large government contracts and hold debts owed by the government. Both are statements and are flagged for review. The group is founded and owned by the Saihood family according to the sources; no register of shareholders was found. Absence of findings is not proof that none exist. Status as of 19 October 2026.

The licence as listed

The list of licensed projects of the National Investment Commission.
Licensing body
National Investment Commission
Licence number
294/2019
Date of grant
11 June 2019
Sector
Industry
Project
Heavy fuel treatment for Wasit thermal power station
معالجة الوقود الثقيل لمحطة كهرباء واسط الحرارية
Licensee
شركة ربان السفينة لمشاريع الطاقة المحدودة (Iraqi)
Licensee's official website
rabanalsafina.comhow we found it
Province
Wasit
Location
واسط
Stated cost
$50 million
State of the project
New licence
The commission's remarks and obstacles
أجازة حديثة

Who is behind the licensee

company (Iraqi limited company according to the National Investment Commission's list; the energy arm of the Raban Al-Safina Group, a private conglomerate of 28 companies founded in 1997 per the Minister of Electricity's biography)
People connected with the licensee
NameRoleLegal statusSource
Saadi Wahib Al-Saihood
سعدي وهيب الصيهود
Founder of Raban Al-Safina Group and founder of the American University of Iraq, Baghdad, per 964 (14 May 2026). Chaldean News (30 March 2026) says he founded the group in the late 1990s.Not charged as of the date of writing
Not charged as of the date of writing. Mustaqila reported on 23 July 2026 that, according to published judicial statements, neither the group nor its founder is accused in the case of Adnan… Read the rest al-Jumaili, the former deputy oil minister for refining. No charge, court ruling, sanction or official finding was found in the sources read. Status as of 19 October 2026.
Document (saved page)964
Ali Saadi Wahib (Ali Wahib Al-Saihood)
علي سعدي وهيب
Minister of Electricity since the vote of confidence of 14 May 2026, born in 1988, formerly executive vice president and chief operating officer of Raban Al-Safina Group, and the founder's son, per 964.Not charged as of the date of writing
Not charged as of the date of writing. 964 reported on 14 May 2026 that his appointment drew reactions over a conflict of interest, because companies of his family have debts owed by the government,… Read the rest and quoted the former MP Raed al-Maliki to that effect. That is criticism by a former MP and not a finding or an accusation of an act. Status as of 19 October 2026.
Document (saved page)964
Hussein Saihood
حسين صيهود
Executive vice president of Raban Al-Safina Group and chief executive of its energy arm RASEP, per the Arab Gulf States Institute in Washington; co-founder and trustee of the American University of Iraq, Baghdad.Not charged as of the date of writing
Not charged as of the date of writing. Named as an executive. No charge, court ruling, sanction or official finding was found in the sources read. Status as of 19 October 2026.
Document (saved page)agsi.org

Links stated in published sources

Each link is attributed to its source. A stated link is not a finding of wrongdoing.
  • Mustaqila reported on 23 July 2026 that an unnamed source asked the Integrity Commission and the Federal Board of Supreme Audit to audit contracts obtained by companies of the Raban Al-Safina Group in the oil refining sector during the period of Adnan al-Jumaili as deputy oil minister for refining, to check supply prices, the need for the equipment and where it is used. The source also questioned the allocation of land for the group's factory at Owairij south of Baghdad and a USD 20 million loan from the Trade Bank of Iraq, without producing the decisions or the loan contract. Mustaqila said it could not verify this independently, that no technical documents or official reports support the claims, and that published judicial statements do not show the group or its founder accused in the al-Jumaili case. The statement is anonymous and the outlet is not one the project treats as credible. It names the group, not this licence, and is recorded as a statement, not as a finding.

    ولا تتوافر حتى الآن وثائق فنية أو تقارير رسمية تثبت الادعاءات بشأن استخدام مواد غير مطابقة، كما لم يظهر في البيانات القضائية المنشورة أن مجموعة «ربان السفينة» أو مؤسسها سعدي وهيب صيهود متهمان في قضية الجميلي.

    mustaqila.comoriginal address

  • 964 reported on 14 May 2026 that the Iraqi parliament gave confidence to the government of Ali Falih al-Zaidi on 14 May 2026 and that Ali Wahib, the son of the group's founder Saadi Wahib, became Minister of Electricity. It said his appointment drew reactions over a conflict of interest, because the family's companies hold large investment contracts with the government, above all in electricity, and have debts owed by the government, which former MP Raed al-Maliki said also applies to the prime minister. The report is about the minister and the group; it does not mention the licence of this entry.

    الأمر الذي لاقى ردود أفعال بسبب تقاطع المصالح، كون الشركات العائدة للعائلة، لديها ديون في ذمة الحكومة

    964media.comoriginal address

What official and press reports say

Official findings
No court ruling, Integrity Commission statement, audit bureau finding or parliamentary report naming the company was found. A request by an unnamed source to audit the group's refining contracts and the criticism of a conflict of interest over the electricity minister are recorded as statements, with no finding.
What became of the project
The National Investment Commission list records licence 294/2019 dated 11 June 2019 for the treatment of heavy fuel for the Wasit thermal power plant (list entry «معالجة الوقود الثقيل لمحطة كهرباء واسط الحرارية») in Wasit, sector industry, nationality Iraqi, at a stated cost of USD 50,000,000. Completion is marked «؟». The recorded obstacle is «أجازة حديثة». The list writes the date as 6 November 2019, a spreadsheet date with day and month apparently transposed. The encyclopedia's licence table reads it as 11 June 2019. No obstacle or completion figure is recorded. No report on this project was found in the sources read.
Other contracts with the state
The National Investment Commission list shows one licence for this licensee. Entries 190 (Maysan Energy Company) and 227 (Al-Amarah Energy Company) of this register record the group's two combined cycle power plants at Maysan and Amarah, which the earlier research ties to the group by project. 964 reports that the group oversees 1,700 MW at the Maysan and Amarah plants and holds contracts with the Ministry of Electricity. Shafaq News reported on 13 September 2025 that the Iraqi government signed with the International Finance Corporation a partnership contract for a teaching hospital worth USD 250 million with «شركات ربان السفينة». The Arab Gulf States Institute describes the group's energy arm.

Sources

  1. مصدر يطالب هيئة النزاهة بتدقيق عقود مجموعة «ربان السفينة» خلال إدارة عدنان الجميليoriginal address, Mustaqila News Agency (statement of an unnamed source), 23 July 2026 Tier D
    طالب مصدر مطلع هيئة النزاهة الاتحادية وديوان الرقابة المالية بتدقيق العقود التي حصلت عليها شركات تابعة لمجموعة «ربان السفينة» في قطاع التصفية النفطي
  2. مصدر يطالب هيئة النزاهة بتدقيق عقود مجموعة «ربان السفينة» خلال إدارة عدنان الجميليoriginal address, Mustaqila News Agency (statement of an unnamed source), 23 July 2026 Tier D
    ولا تتوافر حتى الآن وثائق فنية أو تقارير رسمية تثبت الادعاءات بشأن استخدام مواد غير مطابقة، كما لم يظهر في البيانات القضائية المنشورة أن مجموعة «ربان السفينة» أو مؤسسها سعدي وهيب صيهود متهمان في قضية الجميلي.
  3. أصغر وزير في حكومة الزيدي.. نجل مؤسس الجامعة الأميركية ربان سفينة الكهرباءoriginal address, 964 Media, 14 May 2026 Tier D
    الأمر الذي لاقى ردود أفعال بسبب تقاطع المصالح، كون الشركات العائدة للعائلة، لديها ديون في ذمة الحكومة
  4. أصغر وزير في حكومة الزيدي.. نجل مؤسس الجامعة الأميركية ربان سفينة الكهرباءoriginal address, 964 Media, 14 May 2026 Tier D
    نجل مؤسس الجامعة الأميركية في بغداد “سعدي وهيب”
  5. أصغر وزير في حكومة الزيدي.. نجل مؤسس الجامعة الأميركية ربان سفينة الكهرباءoriginal address, 964 Media, 14 May 2026 Tier D
    ولديها عقود مع وزارة الكهرباء، إذ تشرف على إنتاج 1700 ميغاواط في محطتي كهرباء ميسان، وكهرباء العمارة
  6. Hussein Saihood - AGSIoriginal address, Arab Gulf States Institute in Washington (AGSIW) Tier D
    He serves as executive vice president of the Raban Al Safina Group and CEO of RASEP
  7. Saadi Al Saihoodoriginal address, Chaldean News, 30 March 2026 Tier D
    In the late 1990s, he founded Ship Captain Group (Skipper of the Ship/Rabban Al-Safina-RAS) (punctuation adjusted)
  8. شفق نيوز..العراق يبرم سبعة عقود استثمارية بالشراكة مع مؤسسة التمويل الدولية IFCoriginal address, Shafaq News, 13 September 2025 Tier D
    وعقد شراكة لإنشاء مستشفى تعليمي بقيمة 250 مليون دولار، مع شركات ربان السفينة