Al-Noor Al-Thaqib General Contracting Company Ltd
Investment licence of the National Investment Commission, for the project: Service and collection contract for Zayouna sector districts 710, 712 and 714.
شركة النور الثاقب للمقاولات العامة المحدودة
In short
This licence is held by Al-Noor Al-Thaqib General Contracting Company Ltd, and was granted in 2016. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. No court ruling, arrest warrant, sanctions listing or statement naming this company as accused was found. An official statement of 13 January 2019 on the Al-Ghadeer electricity contract does not name the company, so the status is not raised. Status as of 1 November 2026.
The licence as listed
- Licensing body
- National Investment Commission
- Licence number
- 106/2016
- Date of grant
- 27 October 2016
- Sector
- Energy
- Project
- Service and collection contract for Zayouna sector districts 710, 712 and 714عقد الخدمة والجباية لمحلات قطاع زيونة (710-712-714)
- Licensee
- شركة النور الثاقب للمقاولات العامة المحدودة (Iraqi)
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Baghdad
- Location
- بغداد
- Stated cost
- $6.7 millionThe list gives the cost in dinars. It is converted here at 1,190 dinars to the dollar.
- State of the project
- Completed (100% complete)
Who is behind the licensee
The owners and managers were not identified in the sources that were read.
What official and press reports say
- Official findings
- The Federal Integrity Commission said on 13 January 2019, in a statement carried by Alsumaria News, that the referral of the rehabilitation and collection contract for Al-Ghadeer electricity had no legal basis and that the contract was void automatically. It said that the company had been given its investment licence from the date of signing before the smart metering system was installed, that more than a year and a half had passed since signing, and that the company had not provided the real-estate mortgage required by the mortgage contract. The statement does not name the company. On 21 May 2019 the Federal Integrity Commission also called for a review of the performance of all service and collection companies contracted with the Ministry of Electricity, according to Alsumaria News; it named no company. No court case, audit report, licence withdrawal or sanctions listing naming the company was found.
- What became of the project
- Licence 106/2016 of 27/10/2016: service and collection contract for residential blocks 710, 712 and 714 of the Zayouna sector, stated cost IQD 8,000,000,000. Licence 210/2018 of 27/06/2018: service and collection for blocks 702, 704 and 706 of Al-Ghadeer, stated cost IQD 1,102,799,880. Licence 212/2018, dated 9 July 2018 in the register (the list's own cell reads '7 September 2018', which can be read either way): service and collection for the Palestine Street blocks, stated cost IQD 1,712,122,140. Licence 258/2019 of 23/01/2019, under the shorter name: collection service for Zayouna blocks 716 and 718, stated cost IQD 4,165,290,000. The completion column reads '1' for all four, which the register reads as 100 per cent complete. No source found describes how the contracts have been carried out. On the New Baghdad underground cable project, 964 Media reported residents' complaints about damage from excavation and said that some residents feared a repeat of the Zayouna experience, which it described as not free of faults and cuts. For what such contracts are, Shafaq News of 30 March 2024 quotes the Ministry of Electricity's spokesman Ahmed Moussa as saying that service and collection companies provide a service and not only collection, that the contracts bind both sides, and that they require the company to employ 80 per cent of the ministry's collection staff and to secure their salaries out of a fixed share of 12.9 per cent of the sums collected, the rest going to the ministry. That article concerns the ministry's contracts of 2024, names no company and says nothing about this licensee, so none of it is attributed to the licensee. The terms of the licensee's own contracts are not stated in any source found.
- Other contracts with the state
- Four licences in the commission's list, all electricity service and collection projects in Baghdad: 106/2016 (Zayouna blocks 710, 712 and 714), 210/2018 (Al-Ghadeer blocks 702, 704 and 706), 212/2018 (Palestine Street blocks) and 258/2019 (Zayouna blocks 716 and 718, listed under the shorter name; IQD 4,165,290,000). The web copy on the Basra governorate site (page date 8 March 2019, which looks like a republication, since the first licence is dated October 2016) quotes the Ministry of Electricity's spokesman Musab al-Mudarris as announcing that the Rasafa Electricity Distribution Directorate had signed an investment contract with the company, called the first in Iraq in the distribution sector, for maintenance, smart meters and collection of fees in Zayouna blocks 710, 712 and 714, for five years, renewable. The University of Baghdad's College of Administration and Economics (3 April 2017) names the company and the Rasafa directorate as the two parties to the Zayouna investment project. 964 Media reported on 29 November 2022 that the ministry's spokesman, Ahmed al-Abadi, said the project to replace overhead lines with underground cables in blocks 704 and 706 of New Baghdad had been referred to the company, which he called one of the service and collection companies. No other government contract was found.
Sources
- توقيع أول عقد استثماري في قطاع التوزيع وجباية الأجورoriginal address, Basra Governorate Office (web copy of a news item, page date 8 March 2019), 8 March 2019 Tier D
ابرام مديرية توزيع كهرباء الرصافة عقدا استثماريا يعد «الاول» في العراق في قطاع التوزيع مع شركة النور الثاقب
- مناقشة بحث الدبلوم العالي في تخصص التخطيط الاستراتيجي للطالب ( مصطفى ثائر ثابت )original address, University of Baghdad, College of Administration and Economics, 3 April 2017 Tier D
شركة النور الثاقب للمقاولات العامة المحدودة (القطاع الخاص) وهما طرفي مشروع زيونة الاستثماري
- الحكومة تمنح بغداد الجديدة كهرباءً "تحت الأرض" وتلغي الأعمدة نهائيا (صور)original address, 964 Media, 29 November 2022 Tier D
المشروع أحيل إلى (شركة النور الثاقب)، وهي إحدى شركات الخدمة والجباية
- النزاهة: عقد تأهيل وجباية كهرباء الغدير لا أساس قانوني لهoriginal address, Alsumaria News (statement of the Federal Integrity Commission), 13 January 2019 Tier D
منح الشركة إجازة الاستثمار ابتداءً من تاريخ توقيع العقد تم قبل نصب وتجهيز منظومة المقاييس الذكية
- النزاهة تطالب بإعادة النظر في أداء شركات الخدمة والجباية التابعة للكهرباءoriginal address, Alsumaria News, 21 May 2019 Tier D
دعت هيأة النزاهة، الثلاثاء، إلى إعادة النظر في أداء شركات الخدمة والجباية المُتعاقدة مع وزارة الكهرباء كافة
- ما قصة "شركات جباية الأجور"؟.. شبهات في وزارة الكهرباء العراقية و"شفق نيوز" تفتح الملف المسكوت عنه (names no company; context on the contract model only)original address, Shafaq News, 30 March 2024 Tier D
تشغيل 80 بالمائة من كادر موظفي وزارة الكهرباء مع تأمين رواتبهم
Other licences of the same licensee
- Service and collection project for Al-Ghadeer districts 702, 704 and 706National commission, 27 June 2018, $926,723, Completed
- Service and collection project for Palestine Street districtsNational commission, 9 July 2018, $1.4 million, Completed