This licence is held by Nasiriya Kuwaiti Company for General Trading and Contracting, and was granted in 2015. The holder's documented legal status: "Not charged as of the date of writing". An official body has taken a regulatory measure concerning the holder or the licence, set out below.

Legal status

Not charged as of the date of writing

Regulatory measure: Disciplined by an official body

Licence withdrawn and investment contract cancelled by a decision of the National Investment Commission dated 9 July 2019, which also charged the company with the delay fines. The CAPA Centre for Aviation says the project was reclaimed because the company failed to complete construction. The decision concerns delay in the project and does not accuse the company of corruption; no court ruling, Integrity Commission statement or audit finding naming the company was found in the sources read. Status as of 2 November 2026.

The licence as listed

The list of licensed projects of the Qadisiyah Investment Commission.
Licensing body
Qadisiyah Investment Commission
Licence number
47/2015
Date of grant
2015
The year is read from the licence number.
Note
The National Investment Commission decided on 9 July 2019 to withdraw this licence and to cancel the investment contract with the company; the Diwaniyah commission posted the decision on 15 July 2019. The National Investment Commission's list names the same company for the new Diwaniyah airport and gives no licence number.
Documents of the licensing body
Sector
Transport
Project
Diwaniyah airport project
مشروع مطار الديوانية
Licensee
شركة الناصرية الكويتية للتجارة العامة والمقاولات
Licensee's official website
No official website found (searched 1 November 2026).
Province
Qadisiyah
State of the project
Withdrawn
The commission's remarks and obstacles
قرار سحب اجازة مشروع مطار الديوانية بتاريخ 2019/7/9

Who is behind the licensee

company (Kuwaiti, as the National Investment Commission list gives; the press writes the name Al-Nasriyah, Al Nasriyah Al Kuwaitiyah Co and Al-Nasiriyah Kuwait Company)
People connected with the licensee
NameRoleLegal statusSource
Sheikha Eman
الشيخة إيمان
Chief executive of Al-Nasriyah Engineering Company, quoted on the Diwaniyah airport by the CAPA Centre for Aviation (entry of 1 February 2015). The company name differs slightly from the licensee's, and the tie rests on the project.Not charged as of the date of writing
Not charged as of the date of writing. She is named as an executive and quoted on the project. No charge, court ruling, sanction or official finding was found in the sources read. Status as of 2 November 2026.
Document (saved page)centreforaviation.com

What official and press reports say

Official findings
The National Investment Commission decided on 9 July 2019 to withdraw the licence, to charge the company with the delay fines and to cancel the investment contract (posted by the Diwaniyah commission on 15 July 2019). No court ruling, Integrity Commission statement or Board of Supreme Audit finding naming the company was found.
What became of the project
Iraq Business News reported on 23 January 2015 that the company signed an agreement to build a new airport in Diwaniyah, a USD 1.35 billion airport to be operated by the company for 45 years; the governor, Ammar Al-Madani, said it would create some 8,000 jobs and that 10 per cent of its revenues would go to the provincial government. AviTrader reported on 10 February 2015 that the National Investment Commission awarded the contract, that the first phase, a 1,600 metre runway and a free trade zone, would cost USD 420 million and finish by spring 2017, and that the whole would take five years. On 15 July 2019 the Diwaniyah commission posted a decision of the National Investment Commission dated 9 July 2019 to withdraw licence 47/2015 for the Diwaniyah airport project of the company, to charge the company with the delay fines and the legal and financial consequences, and to cancel the investment contract. The CAPA Centre for Aviation says the Commission reclaimed the project because the company failed to complete construction. On 27 December 2019 the National Investment Commission and the Civil Aviation Authority announced the construction of a new Diwaniyah airport as an investment opportunity, on part of lot 10/1 of sector 24 Al-Fawar. The National Investment Commission list of licences, held in the register, names the same company for the new Diwaniyah airport and marks the licence as withdrawn, with no number, date or cost. No page found shows any building work.
Other contracts with the state
None found. The National Investment Commission list of licences, held in the register, shows no other licence for the company. AviTrader reported on 10 February 2015 that the company would work with the Turkish Doğuş Group on construction and that the airport would be managed by Eyles AMG of Dubai; that is a trade press report of the plan and not a contract seen.

Sources

  1. قرار سحب اجازة مشروع مطار الديوانيةoriginal address, Diwaniyah Investment Commission (official website) Tier A
    سحب الاجازة الاستثمارية المرقمة (47/2015 )لمشروع مطار الديوانية التابع لشركة الناصرية الكويتية للتجارة العامة والمقاولات
  2. قرار سحب اجازة مشروع مطار الديوانيةoriginal address, Diwaniyah Investment Commission (official website) Tier A
    تحميل الشركة كافة التبعات والغرامات التأخيرية وفق القانون
  3. قرار سحب اجازة مشروع مطار الديوانيةoriginal address, Diwaniyah Investment Commission (official website) Tier A
    فسخ العقد الاستثماري المبرم مع الشركه المذكورة اعلاه
  4. Kuwaiti Firm to Build Diwaniya Airportoriginal address, Iraq Business News, 23 January 2015 Tier D
    Kuwait's Al-Nasriyah Company has signed an agreement to build a new airport in Diwaniya.
  5. Kuwaiti firm Al Nasriyah awarded contract to build new Iraq Airportoriginal address, AviTrader, 10 February 2015 Tier D
    Al Nasriyah Al Kuwaitiyah Co (Al Nasriyah), have been awarded a 45 year contract to build and manage a new airport, NADA, in three phases in the Iraqi city of Al Diwaniyah
  6. Al-Qadisiyah/Diwaniya Airport New Airport Profileoriginal address, CAPA Centre for Aviation Tier D
    National Investment Commission has since reclaimed the project due to Al-Nisiriyah's failure to complete construction.
  7. Investment Opportunity: Diwaniya Airportoriginal address, Iraq Business News, 27 December 2019 Tier D
    The National Investment Commission (National Investment Commission) in coordination with the Iraqi Civil Aviation Authority (ICAA) are pleased to announce the investment opportunity of the construction of Diwaniya New Airport