The "steel-frame schools" (Duwaliya) school-building programme: most of the money spent, most schools unfinished (from 2008 to 2021)
In 2008 the Ministry of Education launched a programme to build some 200 schools through private contractors (and more broadly over 1,700 schools), including prefabricated steel-frame designs. OCCRP (September 2021) found that 13 years later most schools had not been finished to standard and most of the money was spent; Daraj put the waste at over USD 850 million. OCCRP adds that in 2011 and 2012 the government took charge of building 1,500 other schools, mostly through state contractors. Parliament referred the steel-frame schools file to the Integrity Commission in 2013 and 2014 among 25 major files. On 29 January 2019 the Integrity Commission said the integrity criminal court in Baghdad had sentenced the ministry's former contracts director in absentia to seven years under Article 340 of the Penal Code over a contract between the Ministries of Education and of Industry and Minerals for six prefabricated schools; he had not told the central contracts committee that the Ministry of Planning had not approved the cost estimates. On 20 February 2019 the Commission described a seven year sentence against him over two contracts for 65 schools awarded to two state companies, with other accused tried separately. On 19 March 2023 the Commission said it had stopped a ministry payment of IQD 1.437 billion for the steel-frame schools to a person sentenced in absentia, a former bank director now heading a contracting company; the cheque had been handed to his son and was stopped at Rafidain Bank's Karrada Maryam branch.
Terms on this page, explained in the glossary: Dinar, Integrity Commission, OCCRP.
- Period
- From 2008 to March 2023
- Sector
- Education and public worksMinistry of Education school construction
- Kind of case
- Media investigation
- Jurisdiction
- Federal Iraq
In short
The main figure in this case is $850 million, at evidence tier D. 3 people and companies are named in it. Their legal status at the date of writing: Convicted (reported) (2); Charged or wanted (1). The page gives the source of every step, and only a court can convict.
How the money moved, according to the sources
Advance payments to contractors without delivery, weak oversight, low-quality work and abandoned sites.
What happened
File referred to the Integrity Commission (2014). The former contracts director was sentenced in absentia to seven years (January and February 2019, as reported by the Integrity Commission); other accused were tried separately. A payment of IQD 1.437 billion was stopped in March 2023 pending investigation.
Open questions
- Contractor list, payments and court outcomes; value per school.
- Identity of the contractor whose IQD 1.437 billion payment was stopped in 2023, and the case in which he was sentenced.
- Outcome of the cases of the other accused tried separately.
People and companies
| Name | Role in the case | Legal status | Detail | As of |
|---|---|---|---|---|
| Former contracts director, Ministry of Education (unnamed) مدير العقود السابق في وزارة التربية (لم يُذكر اسمه) | Former director of contracts, Ministry of Education; member of the central contracts committee | Convicted (reported) | Sentenced in absentia to seven years under Article 340 of the Penal Code by the integrity criminal court in Baghdad, over a contract with the Ministry of Industry and Minerals for six prefabricated schools and two contracts for 65 schools awarded to two state companies (Integrity Commission statements of 29 January and 20 February 2019, reported by Alsumaria). The court issued an arrest warrant and upheld the seizure of his property; the statements describe him as a fugitive. The judgment was not seen. | 19 October 2026 |
| Director of a company contracted to build steel-frame schools, a former bank director (unnamed) مدير شركة متعاقدة لبناء المدارس الحديدية ومدير مصرف سابق (لم يُذكر اسمه) | Director of a company contracted with the Ministry of Education to build steel-frame schools; formerly a bank director | Convicted (reported) | The Integrity Commission said on 19 March 2023 that he had been sentenced in absentia (the case was not stated; the judgment, arrest warrant and seizure order against him were issued through the Karrada misdemeanour court) and that it had stopped a Ministry of Education payment of IQD 1.437 billion due to his company for the steel-frame schools, after the cheque had been handed to his son. The judgment was not seen; the payment was held pending investigation. | 19 October 2026 |
| Other accused in the 65-school contracts case, tried separately (unnamed) متهمون آخرون في قضية عقدي الـ65 مدرسة فُرّقت قضاياهم (لم تُذكر أسماؤهم) | Accused with the former contracts director of the Ministry of Education | Charged or wanted | The Integrity Commission said on 20 February 2019 that criminal cases against a number of other accused, tried separately, were before the courts. Their outcome is not known as of 19 October 2026. | 19 October 2026 |
Sources
- Alsumaria News (Integrity Commission statement)29 January 2019Official statement reported by the mediaTier B
النزاهة: الحكم على مدير عقود في وزارة التربية بالسجن سبع سنوات
Document (saved page)Original addressحكما غيابيا بالسجن لمدة سبع سنوات بحق مدير العقود السابق في وزارة التربية ... عقد بناء ست مدارس باسلوب البناء الجاهز المبرم بين وزارتي التربية والصناعة والمعادن
SHA-256 73509aa097b7…
73509aa097b7378fa21906092d81d139a6f493f32b6ed75b0602d9e9851dc182 - Alsumaria News (Integrity Commission statement)20 February 2019Official statement reported by the mediaTier B
النزاهة تكشف عن تفاصيل الحكم في قضية عقدين لبناء 65 مدرسة
Document (saved page)Original addressإحالة عقدين لبناء 65 مدرسة لشركتين عامتين، مؤكدة صدور حكم بالسجن بحق مدير العقود السابق في وزارة التربية
SHA-256 4e7bdd9e9fcd…
4e7bdd9e9fcddebd374f0cfae261991ee7480c1065373a9e2c51469b3ae2a4d9 - Baghdad Today (Integrity Commission statement)19 March 2023Official statement reported by the mediaTier B
النزاهة تضبط معاملة صرف لبناء المدارس الحديدية "سيئة الصيت"
Document (saved page)Original addressصرف مبلغ (1،437،000،000) مليار دينار إلى أحد المدانين المحكومين غيابياً (صاحب مدير مصرف سابقاً ومدير إحدى الشركات حالياً) المتعاقدة مع وزارة التربية
SHA-256 2e63a7c90388…
2e63a7c903885f320dfbf69def8af2cb00e4d97dbc2d450f31e659beef729c06 - Al-Aalem Al-Jadeed21 January 2014Press reportTier D
البرلمان يحيل 25 قضية فساد الى النزاهة بينها المدارس الحديدية
Document (saved page)Original addressوالذي كان ابرزها ملف المدارس الحديدية
SHA-256 1f6523787007…
1f65237870073eb8189cd9754c047186664114823602ffdf4017b3267d063779 - OCCRP (Assad Zalzali)27 September 2021Press reportTier D
Iraq's Troubled School Building Lesson
Document (saved page)Original addressmost of the schools haven’t been finished to the government’s standards and most of the money is spent