Daiko International Holding Ltd
Investment licence of the National Investment Commission, for the project: Basra residential site.
دايكو العالمية القابضة المحدودة
In short
This licence is held by Daiko International Holding Ltd, and was granted in 2018. The holder's documented legal status: "Not charged as of the date of writing".
Legal status
Not charged as of the date of writing
Not charged as of the date of writing. No court ruling, Integrity Commission statement, audit bureau finding, sanctions listing or credible press accusation naming this company was found in the sources read. Shafaq News reported on 3 June 2021 that the five Baghdad central market licences were withdrawn from the company after no project was carried out. That is a licence withdrawal for non performance and not an allegation of corruption. The National Investment Commission list records the presence of a Popular Mobilization Forces headquarters on one of the market sites; it does not link the company to that body. Owners and managers were not identified. Absence of findings is not proof that none exist. Status as of 19 October 2026.
The licence as listed
- Licensing body
- National Investment Commission
- Licence number
- 235/2018
- Date of grant
- 4 October 2018
- Sector
- Housing
- Project
- Basra residential siteموقع البصرة السكني
- Licensee
- دايكو العالمية القابضة المحدودة (British)
- Licensee's official website
- No official website found (searched 1 November 2026).
- Province
- Baghdad
- Location
- بغداد
- Stated cost
- $230.3 million
- State of the project
- Not reported
- The commission's remarks and obstacles
- عدم استلام الارض لوجود مشاكل
Who is behind the licensee
The owners and managers were not identified in the sources that were read.
What official and press reports say
- Official findings
- Withdrawal of the licences is reported by Shafaq News on 3 June 2021 from the head of the General Company for Central Markets, who said no project had been carried out. No court ruling, Integrity Commission statement or audit finding naming the company was found.
- What became of the project
- The National Investment Commission list records licence 169/2018 أ dated 8 April 2018 (the list gives a spreadsheet date, so day and month may be transposed) for the rehabilitation and development of the Al-Mustansiriya central market in Baghdad, sector commerce, nationality British, at a stated cost of USD 55,280,439. The list marks the licence as: contract not signed. The obstacle recorded is «عدم توقيع العقد مع الجهة المالكة وعدم إصدار إجازة هدم وبإعادة بناء السوق ووجود مقر للحشد الشعبي في وقع السوق», that is, the contract with the owner was not signed, no demolition permit for rebuilding the market was issued, and a Popular Mobilization Forces headquarters stood on the market site. The National Investment Commission list records licence 169/2018 ب dated 8 April 2018 (the list gives a spreadsheet date, so day and month may be transposed) for the rehabilitation and development of the Al-Adl central market in Baghdad, sector commerce, nationality British, at a stated cost of USD 41,723,086. The list marks the licence as: contract not signed. The obstacle recorded is «عدم توقيع العقد مع الجهة المالكة بسبب وجود عقد مسبق بين الشركة العامة للأسواق المركزية وهيئة الحشد الشعبي», that is, the contract with the owner was not signed because of an earlier contract between the General Company for Central Markets and the Popular Mobilization Commission. The National Investment Commission list records licence 170/2018 أ dated 8 April 2018 (the list gives a spreadsheet date, so day and month may be transposed) for the rehabilitation and development of the Al-Salihiya central market in Baghdad, sector commerce, nationality British, at a stated cost of USD 28,703,258. The list marks the licence as: contract not signed. The obstacle recorded is «عدم توقيع العقد مع الجهة المالكة ووجود تجاوز من قبل مجلس محافظة بغداد على ساحة وقوف السيارات وعدم إصدار إجازة بناء.», that is, the contract with the owner was not signed, Baghdad provincial council had encroached on the car park, and no building permit was issued. The National Investment Commission list records licence 170/2018 ب dated 8 April 2018 (the list gives a spreadsheet date, so day and month may be transposed) for the rehabilitation and development of the Al-Amil central market in Baghdad, sector commerce, nationality British, at a stated cost of USD 40,918,936. The list marks the licence as: contract not signed. The obstacle recorded is «عدم توقيع العقد مع الجهة المالكة وعدم إصدار إجازة بناء», that is, the contract with the owner was not signed and no building permit was issued. The National Investment Commission list records licence 171/2018 dated 8 April 2018 (the list gives a spreadsheet date, so day and month may be transposed) for the rehabilitation and development of the Al-Shaab central market in Baghdad, sector commerce, nationality British, at a stated cost of USD 39,443,339. The list marks the licence as: contract not signed. The obstacle recorded is «عدم توقيع العقد مع الجهة المالكة وعدم إصدار إجازة بناء ووجود مقر لحماية المنشآت», that is, the contract with the owner was not signed, no building permit was issued, and a facilities protection headquarters stood on the site. The National Investment Commission list records licence 196/2018 dated 16 April 2018 for the Al-Muftiya entertainment project in Basra, sector housing, nationality British, at a stated cost of USD 234,454,755. The obstacle recorded is «لم يتم أبرام العقد الاستثماري مع المستثمر بسبب أحداث البصرة .», that is, the investment contract was not concluded because of the events in Basra. The National Investment Commission list records licence 235/2018 dated 4 October 2018 (the list gives a spreadsheet date, so day and month may be transposed) for a residential site in Basra, recorded in the list under Baghdad in Baghdad, sector housing, nationality British, at a stated cost of USD 230,268,486. The obstacle recorded is «عدم استلام الارض لوجود مشاكل», that is, the land was not received because of problems. The National Investment Commission list records licence with no number for the Al-Muftiya entertainment project (a second row), sector housing, nationality British. The list marks the licence as: withdrawn. The obstacle recorded is «تم سحب الاجازة», that is, the licence was withdrawn. Shafaq News reported on 3 June 2021 that the Ministry of Commerce announced that the General Company for Central Markets had recovered its five markets from the UAE company Daiko. The company's general manager, Zahra al-Kilani, said that after extensive discussions with the National Investment Commission the five investment licences for rehabilitating and developing the central markets in Baghdad were withdrawn from the company, three years after the former cabinet referred the matter to the National Investment Commission, and that no investment project had been carried out in the buildings. The National Investment Commission list marks one Al-Muftiya row as withdrawn and records no completion for any licence. The press calls the company Emirati and the National Investment Commission list gives British nationality; the difference is not explained.
- Other contracts with the state
- The National Investment Commission list shows eight rows under this name: five central market licences in Baghdad (169/2018 A and B, 170/2018 A and B, 171/2018), the Al-Muftiya entertainment project in Basra (196/2018), a Basra residential site recorded under Baghdad (235/2018), and a second Al-Muftiya row marked withdrawn. No other state contract was found.
Sources
- Iraqi authorities withdraw five investment licenses from Emirati company Daikooriginal address, Shafaq News, 3 June 2021 Tier D
The Iraqi Ministry of Commerce announced that the General Company for Central Markets had recovered its five markets from the UAE Daiko Company.
- Shafaq News..Iraqi authorities withdraw five investment licenses from Emirati company Daikooriginal address, Shafaq News Tier D
the five investment licenses for rehabilitating and developing central markets in Baghdad were withdrawn from the Emirati company
- Shafaq News..Iraqi authorities withdraw five investment licenses from Emirati company Daikooriginal address, Shafaq News Tier D
No investment projects had been implemented in these buildings located in vital areas of Baghdad
Other licences of the same licensee
- Rehabilitation and development of the central markets, Al-Mustansiriya CentralNational commission, 8 April 2018, $55.3 million, Contract not signed
- Rehabilitation and development of the central markets, Al-AdlNational commission, 8 April 2018, $41.7 million, Contract not signed
- Rehabilitation and development of the central markets, Al-SalihiyaNational commission, 8 April 2018, $28.7 million, Contract not signed
- Rehabilitation and development of the central markets, Al-AmilNational commission, 8 April 2018, $40.9 million, Contract not signed
- Rehabilitation and development of the central markets, Al-ShaabNational commission, 8 April 2018, $39.4 million, Contract not signed
- Al-Muftiya entertainment projectNational commission, 16 April 2018, $234.5 million, Not reported
- Al-Muftiya entertainment projectNational commission, Withdrawn